After the investigation of the site and calculating the weight of
steel members , the erection works is divided into 3 stages as the
following :
Stage 1:Erection of structural steelworks at 4F in sequence by a
300-T crawling crane for 3 blocks.
Stage 2:Erection of structural steelworks from 5F to ROOF by an
internal CTL400 tower crane for each block .
Stage 3:Erection of auditorium structural steelworks and dismantling
of 3 internal CTL400 tower cranes by an external WK160B tower crane.
Delivery of steel members is carried by tank cranes and trailers
on site.
……